Sorry but this form will not work without cookies enabled. Please adjust your browser settings to enable cookies to continue. For more information on how to do this please see our.

Emergency/Info Notice
  • Highest Quality Learning

    Our personalized approach engages and challenges students, empowering them to reach their highest potential.

    High Quality Learning

  • Join Us

    We welcome you to join our vibrant, international community of learners.

    Campus

  • Ask Us Anything

    Speaking directly with us is the best way to get your questions answered quickly. We look forward to hearing from you.

    Early Years Learning

  • Exceptional Teachers

    Our highly qualified, energetic and experienced staff is focused on developing children's unique learning styles.

    BISC-SL Teacher

  • Our Unique School Day

    BISC-SL students love coming to school, the day is always inspiring.

    Be Ambitious!

  • Join Our Family

    We welcome you to our BISC-SL community. From day one, you and your child will feel at home with us.

    BISC-SL Community

  • Go, Bulldogs!

    Our varied athletics programming fosters sportsmanship, competition and discipline.

    BISC-SL Athletics

  • Join a Virtual Discovery Meeting

    Nothing can replace a face-to-face visit and tour of our school – but with school closures and travel restrictions around the world, a Virtual Discovery meeting is the next best thing.

    Virtual School

Construction Update - October 2014

  • south loop construction
  • south loop construction
  • south loop construction
  • south loop construction
  • South Loop Construction

Here's the latest progress update on construction at the new South Loop campus:

  • The northeast corner of the building is in development of framing and progress is moving on schedule
  • Concrete deck pouring at the northwest corner is now completed
  • No roofing work took place last week due to the bad weather in Chicago; however. it is back in progress this week as they continue to add the waterproofing level as the base of the roof plan
  • Gym walls are now 75% finalized and they are continuing with this work
  • Framing on the second floor of the building is making good progress and it is now possible to see the classroom plans as they appear in floor plans
  • The electrical subcontractor has been on site providing wire running and has been able to make significant progress to prep the spaces for conduit inclusion
  • Boys and Girls locker rooms have walls up and installed and plumbing rough-ins completed. 
  • Basement framing is all but finalized and the team are now preparing for door framing, which will begin in the next two weeks